|
By JODI DEAL - COALFIELD PROGRESS
Published January 13, 2006
http://www.zwire.com/site/news.cfm?BRD=1283&dept_id=158550&newsid=15924395&PAG=461&rfi=9
One-third of a $5 million General Assembly appropriation for water and sewer
projects in Southwest Virginia is headed for the Lenowisco Planning District.
The $1.6 million award will connect 467 households with public water and 168
households with sewer service, with a total of 635 homes served.
The money has been split as equally as possible among the eligible projects in
each county served byt the planning district, including Wise, Lee and Scott
counties, along with the city of Norton, Lenowisco planner Lou Ann Johnson says.
Gov. Mark Warner made the announcement Thursday.
The Cumberland Plateau and Mount Rogers planning districts also got $1.6 million
each. The funds will be distributed through the Virginia Department of Housing
and Community Development, and will serve more than 1,000 households. That
includes connecting about 800 citizens with clean and safe public water.
All of the projects funded by the General Assembly appropriation, referred to as
the Southwest Virginia Water and Wastewater Fund, were identified as "high
priority" in a recent state assessment of Southwest Virginia's water needs.
The projects planned in Wise County and the City of Norton, which account for
about $547,000 of the local share of the water/wastewater fund, include:
* Banner/ Sandy Ridge Interconnect: About $290,000 will be used toward the
connection of two Wise County Public Service Authority pump stations in the
Banner section of Coeburn and on Sandy Ridge.
The interconnect would not serve any new households, but would allow the town of
Coeburn and the county PSA to end a water-swapping agreement that, since the
early 1990s, has limited the capacity of Coeburn's water treatment plant. With
the connecting pipes, PSA will be able to serve customers on Sandy Ridge without
help from the town, allowing Coeburn to serve new customers in Flatwoods.
Lenowisco and the county PSA have worked together to seek grant funding for the
project. According to Johnson, the remaining $373,000 may be covered by a grant
they have applied for from the Virginia Department of Health. Johnson doesn't
expect to hear news on that grant until June but, in the meantime, she says, the
water/wastewater fund money can be used to work on planning.
That way, if the funding comes through, the project can move forward as soon as
VDH grant money is awarded, she added.
* Flatwoods water extension: About 80 homes in the Flatwoods community just
outside of Coeburn will receive public water service from the town as a result
of this project. About $203,000 of the water/wastewater appropriation will go
toward this project, in addition to a $1 million community development block
grant from DHCD and a $40,000 planning grant from Lenowisco. Now that the
project has full funding, Johnson noted, construction might begin as soon as
May.
* Riverview sewer: This project will provide eight homes in the Riverview
community, just south of Coeburn, with sewer service. Lenowisco has directed
$54,000 of the water/wastewater fund to this project, and the county PSA has
invested $40,000. The total, $94,000, should be enough to pay for a preliminary
engineering report, a rate study, other planning needs, materials and
installation, Johnson said. She added that plans are complete, and the project
should be under construction by April and completed by May.
* Norton dam: The city will receive $50,000 from the water/wastewater fund to
pair with $50,000 it has received in other General Assembly appropriations to
pay for engineering services on the dam project, Johnson said.
Once the city has a definite plan, including construction costs and construction
documents, it will be able to seek funds to get the construction underway.
"The $100,000 is a drop in the bucket compared to what this will
cost," Johnson noted, but it's a start. The engineering should be completed
by September, she said.
The city of Norton needs to strengthen the earthen dam at its reservoir so it
meets state dam safety requirements. To coat the dam with concrete may cost
about $2.44 million, and to raise its capacity along with the needed repairs
will cost about $3.46 million, according to preliminary estimates.
City Manager Ernie Ward said in August that he hopes to see the project
completed by the fall of 2008.
OTHER LENOWISCO PROJECTS
Other projects funded with the remaining $1.03 million from the water/wastewater
fund include:
* Rose Hill Sewer: Will provide 160 Lee County homes with sewer service. The
project has received $500,000 from the water/wastewater fund and $500,000 from
DHCD, and is currently under construction.
* Occonita Loop water project: Will serve 360 homes in Occonita, located in Lee
County. About $203,000 from the water/wastewater fund completes the funding for
this $7.14 million project. Other grants and loans have come from VDH and the
USDA Rural Development Agency. Construction is set to start this summer.
* Manville/Red Hill Water extension: The town of Gate City will begin providing
public water to 17 households in two Scott County when this project, slated to
start within the next month, is completed in early 2007. About $2.1 million of
the cost came from the Virginia Department of Health, and the remaining $203,000
came from the water/wastewater fund.
* Mabe/Stanleytown Water Extension: Ten homes will get water service as a result
of this extension, which will cost about $105,000. The full cost of the project
will be covered by water/wastewater fund money.
|